Rosebud’s Long Struggle
(This article follows up on previous AWI Quarterly
articles and incorporates historical information from Chapter 5 of Marlene
Halverson’s report “The Price We Pay for Corporate Hogs,” published by
Institute for Agriculture and Trade Policy. Please view the report online at
www.iatp.org/hogreport)
In 1998, Sun Prairie, a Nebraska partnership, entered
into a lease arrangement with the Rosebud Sioux Tribal Council of South Dakota
that would have created the world’s third largest hog factory on Rosebud Tribal
Lands. In turn, Sun Prairie contracted with Bell Farms, a North Dakota
corporation, to manage and operate the hog factory. Under the lease agreement,
the Rosebud Sioux Tribe was to provide tribal lands, water and human resources
for running the farm in return for one quarter of the hog factory’s profits and
the opportunity to purchase the factory at 50 percent of its original cost at
the end of a 15-year amortization period. The lease arrangement had the
approval of the local office of the U.S. Bureau of Indian Affairs (BIA) in
Aberdeen.Some alert Tribal members, having heard about the
adverse environmental, animal and human welfare consequences of hog factories
elsewhere, learned of the lease agreement. Recognizing how culturally and
economically disadvantageous the lease agreement would be for the Tribe, they
began what became a tortuous, years-long struggle to extricate the Tribe from
the agreement.
Tribal members and neighboring
ranchers who opposed the lease agreement formed a group called the
Concerned Rosebud Area Citizens and sought help from South Dakota
Peace and Justice Center – which, in turn, sought help from Prairie
Hills Audubon Society and Humane Farming Association in fighting the
hog factory. These groups brought suit in Federal District Court in
Washington, DC against the US Bureau of Indian Affairs because the
local Bureau’s approval had violated the National Environmental
Policy Act (NEPA) by not requiring an Environmental Impact Statement
(EIS) prior to approval.
When the BIA’s attorneys at the
Department of Justice looked into the case, they quickly realized
they would lose and proposed a settlement, which was negotiated in
about two months. However, in January 1999, Assistant Interior
Secretary for Indian Affairs Kevin Gover voided the lease because
the environmental review process had been inadequate, and an EIS
should have been required. Sun Prairie/Bell Farms then sued the BIA
in South Dakota’s Federal District Court, aiming to overturn Gover’s
decision. The Department of Justice then defended the BIA (the
government), side by side with the opposing groups.
Federal District Judge Charles
Kornmann quickly issued the first of a series of preliminary
injunctions against the government, directing it and the opposing
groups not to interfere with construction of the hog factory until
he had studied the case and decided whether to make his injunctions
final. His injunctions had the effect of getting the construction
on track and keeping it there. As Kornmann studied the case, a new
Tribal election took place and Tribal members voted in a Tribal
Council whose members opposed the hog factory project. The new
Tribal Council quickly called for a referendum of the people
regarding acceptance of the factory. In the referendum, the hog
factory was rejected by a majority of the voting Tribal members.
However, during the year it took
Judge Kornmann to decide to make his temporary injunction final, one
of the proposed hog sites was completed and put into operation.
Once Kornmann made the temporary injunction against the government
and opposing groups final, the Department of Justice (on behalf of
BIA) and the new Tribal Council could appeal the injunction in the
Federal 8th Circuit Court of Appeals, which they did.
Eventually, the Court of Appeals ruled in favor of the hog factory
opponents, overturning Judge Kornmann’s injunctions and upholding
the BIA’s declaration that the lease was invalid. Nevertheless,
construction had proceeded in the meantime, and another of the 13
sites had been completed and put into operation.
Sun Prairie/Bell Farms then
appealed the Court of Appeals ruling to the US Supreme Court. AWI
reported on an amazing victory for the Tribe (Spring
2003 AWI Quarterly): the US Supreme Court had
refused to hear Sun Prairie/Bell Farms’ case, upholding the eighth
Circuit Court of Appeals decision in favor of the opponents. The
Supreme Court’s refusal to hear the case confirmed
that the lease agreement was legally invalid, and Sun Prairie/Bell
Farms had no legal right to operate on Tribal lands. On March 6,
2003, the Rosebud Tribal Council voted unanimously to shut down the
two operating hog factory sites and remove them from Tribal lands.
The victory, however, was short lived.
Not giving up so easily, Sun
Prairie/Bell Farms brought suit in Federal District Court of South
Dakota against the BIA and Rosebud Sioux Tribe, demanding financial
damages and alleging the Tribe (1) violated the “Contracts Clause”
of the US Constitution and (2) profited from “unjust enrichment.”
In an action that was inexplicable in light of previous court
actions validating the Tribe’s and the BIA’s position, District
Court Judge Richard Battey said he agreed with Sun Prairie/Bell
Farms in the matter, although he did not make a ruling that the
Tribe or Department of Justice (on behalf of BIA) could have
appealed. Instead, Judge Battey simply let his opinion be known and
ordered the parties to try to settle the dispute among themselves.
Tribal members who had fought the
lease agreement were not in favor of settling now that their case
against the hog factory had been won. After all, their legal
position was sound. The highest court in the land had refused to go
against the Appeals Court ruling that had given them their victory.
Therefore, Sun Prairie/Bell Farms really had had no defensible
grounds on which to sue for damages. Neither the Tribe nor the BIA
was legally liable. Attorney Jim Dougherty, who had successfully
guided the Tribe through the legal minefields that had resulted in
the Appeals Court victory, pointed out that the “Constitutional”
claim was frivolous because the Tribe is not subject to the US
Constitution. Furthermore, the Tribe could hardly be guilty of
unjust enrichment.
In order for that to be the case,
it would have had to have received a benefit, been aware that it was
receiving a benefit and it would have had to be shown it was
inequitable for it to retain the benefit without paying for it –
none of which could be shown. In five years of operation, the Tribe
had been presented with only one profit sharing check for $11,000,
which it had turned down. Moreover, under South Dakota law, a claim
of “unjust enrichment” can only be pursued if the claimant has
“clean hands.” Dougherty noted that Sun Prairie/Bell Farms had
violated provisions of the lease many times by never having paid
TECRO fees, rent or water use fees.
However, an election had been held
and another Tribal Council (the third to have dealt with the issue)
was in place. The new owner of Sun Prairie/Bell Farms CEO Greg
Fontaine had appeared before the new Tribal Council and claimed the
Tribe was liable for millions of dollars. In an outrageous and
inexplicable abandonment of both the Rosebud Sioux Tribe and the
law, Assistant US Attorney General Tom Sansonetti (who has since
resigned) told the Tribe the government would admit liability for
having acted illegally in 1999 when the BIA voided the lease
agreement. This applied pressure to the Tribal Council to settle
the case according to terms the Department of Justice had negotiated
with Sun Prairie/Bell Farms.
Perhaps the new Tribal Council
members were more easily intimidated by Sun Prairie/Bell Farms than
the previous Tribal Council had been, or perhaps they doubted the
Tribe and the hog factory opponents could win in Judge Battey’s
court, given that Judge Battey had let it be known where he stood.
Bullying and intimidation by Sun Prairie/Bell Farms undoubtedly also
had an effect. On April 27, 2005, the new Tribal Council voted 9-7
to accept the settlement offer the government had negotiated. Four
Council members did not vote, and Tribal members asserted that some
Council members voted against straw votes in their own
constituencies, which proved Tribal members did not favor the
settlement.
Sun Prairie CEO Fontaine and new
Tribal Council President Charles Colombe – who, some said, had
favored the hog factory all along – praised the settlement. Under
the terms of the settlement, no new hog facilities are to be built,
but the existing two sites (producing about 192,000 hogs per year)
are allowed to operate for 20 years. Sun Prairie/Bell Farms must
pay rent to the Rosebud Sioux Tribe of $120,000 per year; $15,000
per year for water use at the site where wells have been drilled;
$1.35 per 1,000 gallons of water for three years and $1.50 per
1,000 gallons thereafter and $131,000 for past water usage. Most of
the other terms of the original lease agreement would stand.
Yet the agreement still does not
guarantee environmental justice, safe and fair conditions for Tribal
workers or humane conditions for the pigs who have received
shockingly cruel treatment, as documented by photographs and
interviews with Rosebud farm laborers in legal petitions by Humane
Farming Association to the South Dakota Attorney General (Fall
2004 AWI Quarterly). The hog factory has not shown a
profit, except in its first year. Dougherty asks, given that Sun
Prairie/Bell Farms have consistently shown bad faith to date by not
paying fees and rent, what guarantee is there that they will
suddenly become reliable partners? On May 19, 2005, Judge Battey
approved the settlement.
Several Tribal members, including
those from Rosebud Grassroots Resistance Against Oppression and
Justice, said they plan to contest the settlement. Dougherty said
HFA, which has paid legal costs to date, would continue to fight for
environmental justice and the rights of the Tribal members in the
courts, should the Tribal members wish it. On June 24, 2005, after
the spring 2005 AWI Quarterly had gone to press, concerned
Rosebud Area Citizens, Humane Farming Association, South Dakota
Peace and Justice Center and Prairie Hills Audubon Society of
Western South Dakota filed a new suit in Federal District Court in
Washington, D.C. The groups say the BIA cannot approve any
agreement that does not require an EIS. “We would like to see the
deal suspended until they have done a complete environmental
review,” said Jim Dougherty.
|